The California High-Speed Rail Project Illustrates America’s Transit Issues

Slow progress and a bloated budget have plagued the High-Speed Rail project linking San Francisco to Los Angeles, exposing deeper issues with American transit projects.

4 minute read

May 22, 2022, 11:00 AM PDT

By Eric Carlson

@EricTheUrbanist


A conceptual rendering of three high-speed rail trains. The middle train is orange; the other two are black.

tostphoto / Shutterstock

Believe it or not, it’s been 58 years since the Shinkansen, the world’s first bullet train, first debuted in Japan in 1964. During a five-year construction period, the project completed 320 miles (ca. 515 km) of track, eventually achieving the three-hour service it had projected.

Over that same time period, the United States has built zero miles of high-speed rail (save a few short stretches of the Acela line in the Northeast United States that achieve speeds of about 150 mph). Meanwhile, the fact that the technology still hasn’t come to the United States has deflated a generation of hopes.

The first response to the country’s lack of high-speed rail (HSR) is… why? After all, the United States is one of the richest nations in the world, and could easily afford it. The country has been able to build endless expanses of interstates and highways, yet somehow neglected to implement an effective, well proven transportation technology for moving people quickly and efficiently.

There are reasons to point to, of course. The realities of American car culture, as well as the vast open spaces and relatively low population density in the United States, are the main issues brought up when explaining the country’s lack of HSR infrastructure.

Yet this trend could still change. There is at least one project still pushing toward that dream: The California High-Speed Rail project, which, despite ballooning costs, a slow pace, and constant political backlash, still continues to make progress.

The real question is: Will it ever be finished?

The California Project

The California high-speed rail project between San Francisco and Los Angeles continues to make strides, even if its progress is achingly slow. The Environmental Impact Report for the San Jose to Merced route was recently approved, signaling another milestone for the project.

Despite this progress, rail passengers still won’t see the San Jose to Merced route finished until 2031. If nine years feels like a long time to wait, it will be decades more before completion of the whole Los Angeles to San Francisco route.

“Why is it taking so long?” is the knee-jerk question to such news. It’s not terribly controversial that a high-speed line between San Francisco and Los Angeles would be beneficial to the state (though detractors would make you think so). Even for supporters, waiting decades for such a project to be finished not only feeds the flames of criticism, but weakens the already tenuous political will behind it.

The projected timeline has inspired almost every journalist covering the construction to take turns lamenting its progress, even as they churn over the starry-eyed, optimistic quotes of the project’s spokesmen.

Just a month ago, the New York Times took a swing at an explanation, linking the slow progress to general infrastructure problems in the United States. This sentiment was encapsulated by the story’s quote from scholar Yonah Freemark: “We just have a fundamental problem in the United States of building large projects.”

Yonah hits the problem right on the nose, and it only gets worse when we compare it to similar projects around the world. Over the last few decades, while the United States has been squabbling over high-speed rail projects, China quietly built over 20,000 miles of high-speed rail lines in about 20 years. Chinese authorities have estimated the mileage will be close to 70,000 kilometers by 2035, a year in which San Francisco and Los Angeles will still not be connected by high-speed rail.

To understand why and come up with a solution, one must understand some core problems facing the implementation of high-speed rail in the United States.

America’s Rail Problems

In the United States, transit infrastructure is expensive to build. The country comes in at the 6th-most-expensive place for transit projects, coming behind countries that build more tunnels, thus adding to their cost. The United States doesn’t have that excuse, with the high cost attributed to contentious planning phases, legal troubles, and hurdles such as environmental reviews.

Adding to the cost is a lack of cohesion in development patterns. Without a unifying vision linking development and rail projects, the country continues to get more car-dependent sprawl. Though high-speed rail would effectively link city centers, the momentum for car culture is so strong in the United States that transit projects often have to waste time proving their right to exist.

Behind all this, though, a lack of political will ultimately dooms many rail projects. The interstate system, America’s last true mega-project, took enormous funding and push from the Federal government. Such forethought and initiative seems to be a thing of the past.

Will there be a change? It’s hard to say. But if the United States poured its vast resources into finishing the California project quickly and efficiently, the path ahead would be much clearer.

Eric Carlson is a writer, urban planner, and designer with degrees in both Journalism and Urban Planning. His passions include high-speed rail, walkable neighborhoods, and urban design. He writes and manages publications on Medium about urban planning and music, and has been featured in the publications Fanfare and Age of Awareness. Find his work online and on LinkedIn.

An aerial view of Milwaukee’s Third Ward.

Plan to Potentially Remove Downtown Milwaukee’s Interstate Faces Public Scrutiny

The public is weighing in on a suite of options for repairing, replacing, or removing Interstate 794 in downtown Milwaukee.

August 27, 2023 - Milwaukee Journal Sentinel

Portland Bus Lane

‘Forward Together’ Bus System Redesign Rolling Out in Portland

Portland is redesigning its bus system to respond to the changing patterns of the post-pandemic world—with twin goals of increasing ridership and improving equity.

August 30, 2023 - Mass Transit

Conceptual rendering of Rikers Island redevelopment as renewable energy facility

Can New York City Go Green Without Renewable Rikers?

New York City’s bold proposal to close the jail on Rikers Island and replace it with green infrastructure is in jeopardy. Will this compromise the city’s ambitious climate goals?

August 24, 2023 - Mark McNulty

A rendering of the Utah City master planned, mixed-use development.

700-Acre Master-Planned Community Planned in Utah

A massive development plan is taking shape for lakefront property in Vineyard, Utah—on the site of a former U.S. Steel Geneva Works facility.

August 31 - Daily Herald

A line of cars wait at the drive-thru window of a starbucks.

More Cities Ponder the End of Drive-Thrus

Drive-thru fast food restaurants might be a staple of American life, but several U.S. cities are actively considering prohibiting the development of new drive-thrus for the benefit of traffic safety, air quality, and congestion.

August 31 - The Denver Post

Air pollution is visible in the air around high-rise buildings in Dhaka, Bangladesh.

Air Pollution World’s Worst Public Health Threat, Report Says

Air pollution is more likely to take years life off the lifespan of the average human than any other external factor, according to a recent report out of the University of Chicago.

August 31 - Phys.org