Long awaited improvements on the Amtrak route between Chicago and St. Louis are being delayed again, this time because of trouble installing positive train control (PTC).
Faster rail service will not be ready by the end of this year as the Illinois Department of Transportation (IDOT) had once hoped. Trains are still unable to exceed 70 miles per hour along the Alton-Granite city corridor, but when work is done, trains will be able to move at 90 mph speeds across the whole route. IDOT now says that improvement will occur in 2020, but has yet to set a date for when train will reach 110 mph speeds the project originally sought.
"The time needed to install and test a new GPS-related safety technology positive train control, is the reason for the longer-than-expected implementation, officials say," Mark Schlinkmann reports for the St. Louis Post-Dispatch. Positive train control (PTC) is a federally mandated safety protocol that was not required when the project started. "The upgrade of the corridor, begun in 2010 and largely finished in 2017, also includes installation of new rails and concrete ties, new Amtrak stations in Alton and elsewhere and improved street crossing gates to keep vehicles from weaving around crossing bars," Schlinkmann writes.
Many upgrades to the route not related to PTC are already complete. "Other improvements were aimed at reducing delays that sometimes make trips longer than scheduled, such as adding or lengthening second-track segments and sidings so two trains can run simultaneously in more areas," Schlinkmann reports.
FULL STORY: Faster speeds on Amtrak route to Chicago delayed again
‘Forward Together’ Bus System Redesign Rolling Out in Portland
Portland is redesigning its bus system to respond to the changing patterns of the post-pandemic world—with twin goals of increasing ridership and improving equity.
Plan to Potentially Remove Downtown Milwaukee’s Interstate Faces Public Scrutiny
The public is weighing in on a suite of options for repairing, replacing, or removing Interstate 794 in downtown Milwaukee.
Can New York City Go Green Without Renewable Rikers?
New York City’s bold proposal to close the jail on Rikers Island and replace it with green infrastructure is in jeopardy. Will this compromise the city’s ambitious climate goals?
700-Acre Master-Planned Community Planned in Utah
A massive development plan is taking shape for lakefront property in Vineyard, Utah—on the site of a former U.S. Steel Geneva Works facility.
More Cities Ponder the End of Drive-Thrus
Drive-thru fast food restaurants might be a staple of American life, but several U.S. cities are actively considering prohibiting the development of new drive-thrus for the benefit of traffic safety, air quality, and congestion.
Air Pollution World’s Worst Public Health Threat, Report Says
Air pollution is more likely to take years life off the lifespan of the average human than any other external factor, according to a recent report out of the University of Chicago.
Placer County
City of Morganton
HUD's Office of Policy Development and Research
Dongguan Binhaiwan Bay Area Management Committee
City of Waukesha, WI
Los Angeles County Metropolitan Transportation Authority
Indiana Borough
Urban Design for Planners 1: Software Tools
This six-course series explores essential urban design concepts using open source software and equips planners with the tools they need to participate fully in the urban design process.
Planning for Universal Design
Learn the tools for implementing Universal Design in planning regulations.